So, I got and completed my first 80% lower recently. Someone asked about the experience so here is my opinion.

Would I do it again? ...Maybe. The work wasn't hard but it was time consuming.
The whole process took me about 5 hours over the total of three evenings in the garage. (I am sure the process gets faster the more you do.) Plus I have a huge mess to clean up. But that's my fault since I don't have a shop vac and forgot to borrow one from work.

I didn't have the tools other than the drill press. Luckily, I was able to borrow a jig and router. Total cost for me to have a lower has been $20 + whatever finishing is going to be.

For me it comes down to cost and time, if you are doing one (1) it just isn't cost effective if you don't happen to already own the tools. Plus four to five hours to get it done.
If you plan on doing several or even a build party with friends then I can see the draw.

So, final thoughts.
  • It was fun.
  • I am glad I did it.
  • Being able to have everything shipped to your doorstep is awesome.
  • Doing only one is pricey.
  • It's slightly time consuming.
  • It's messy.
  • I can see the benefits of having all the equipment and several inexpensive 80% lowers stashed away, for whatever.



Double Snek by Damage Photos, on Flickr


DSC_0020 by Damage Photos, on Flickr